Order of Landscaping Phases for Developments in the Boland

Summers in the Cape Winelands are dry and hot, and the south-easter strips moisture from new planting within days. On developments in Paarl, Wellington, Stellenbosch and Somerset West, landscaping usually arrives at the end of a building programme, when time and budget are thinnest. That is also when sequencing mistakes cost the most.

Landscaping can be split into as many phases as a project needs. The order of those phases stays the same. Paving comes first, then trees, then beds, and lawn last, with mulching and fertilising after it. Irrigation is checked somewhere in between.

Paving First, Because Levels Follow It

Paving is the most expensive element in most landscape scopes, and it sets the finished levels for everything around it. Bed edges, lawn heights, drainage falls and retaining details all connect to the paving line. If paving is built after planting, levels have to be re-cut and finished areas are disturbed.

Drainage is a good example. On the Swartland clay of Durbanville and the lower terraces of Wellington, water moves slowly and winter waterlogging is common. Falls set at paving stage decide where that water goes. Fixing them later means lifting paving or regrading planted ground.

Paving is also the phase most likely to be cut for budget. Where the full scope cannot be built at once, driveways, entrances and main walkways go first, because they carry the levels the rest of the work depends on.

Trees and Beds Before Anything Is Laid

Trees are the largest plants on site, and planting them needs machinery, deep holes, stakes and access for delivery trucks. That traffic would wreck finished beds, so trees go in before bed preparation starts. Staking matters in the Boland, where a young tree in an exposed position can be rocked loose by the south-easter before its roots have anchored.

Beds follow trees. Bed preparation depends on the soil profile. Granite slope soils around Paarl mountain and Franschhoek hold water and suit deep-rooted shrubs, while the sandy valley floor needs heavy organic matter to hold anything at all. Doing this work once, after the trees are in, avoids compacting prepared soil with a second round of earthworks.

For quantity surveyors, the benefit is plain. Plants established in correctly prepared beds need fewer replacements in the first year, and replacement cost is one of the largest avoidable lines in a landscape budget.

Irrigation Checked Along the Way, Lawn Last

Planting without irrigation in a Boland summer is an expensive mistake. Irrigation does not need its own long phase, but it needs a check before beds and lawn go in. Where an estate already has a working system, new areas can usually be connected to it with a quick extension. The points to confirm are that the controller (Hunter, Rain Bird and Irritrol are common on estates) has spare stations, that lawn and bed zones run separately, and that water pressure holds at the new tie-in. Zoning, hydraulic design and commissioning are separate steps, and each needs to be signed off.

Lawn, mulching and fertilising come last. A newly planted lawn needs to be left alone to settle. Once it is down, nobody should be walking across it with ladders, paint buckets or building materials. Contractors and painters working near a fresh lawn leave compaction and dead patches that show up at handover inspection. Mulch goes onto beds once planting is finished. Lawn fertiliser goes on the lawn only, and standard fertilisers must stay away from fynbos and Proteaceae plantings, where phosphorus damages the plants.

Frequently Asked Questions

Can landscaping phases overlap with the final building works?
Paving and tree planting can start before the last trades leave, provided access routes are agreed. Lawn should wait until painters, plasterers and roofers have finished, because foot traffic is what damages new lawn most.

What happens if the lawn is laid before the beds?
Bed preparation and planting involve digging, wheelbarrow traffic and soil spillage. All of that damages a lawn that is still settling, and repairs add cost and delay handover.

Does the order change if paving is postponed for budget reasons?
The order stays the same. If paving is delayed, finished levels for beds and lawn should still be set out against the planned paving line, so the later work does not force regrading.

How early should irrigation be checked?
Before beds are planted. Confirming controller capacity, zone layout and water pressure at that stage is far cheaper than adding stations after lawn is down.

About Greenfingers Landscaping

Greenfingers Landscaping works on developments and estates across Paarl, Wellington, Franschhoek, Stellenbosch, Somerset West, Durbanville and Bellville. Coenie and Susan Slabbert are on site themselves, which means sequencing decisions are made against real levels and real contractor programmes. Where a project needs phasing advice before landscaping starts, that conversation is best had before the paving contractor is appointed.

About Green Fingers

Our team, led by founder Susan Slabbert and her son Coenie, is dedicated to a hands-on approach, ensuring every detail is meticulously considered and executed. Susan’s recognized garden designs and Coenie’s integration of modern technology have positioned us as a highly-rated company within prestigious estates like Pearl Valley and Val de Vie.